![]() |
|
|||||||
![]() ![]() ![]() |
|
|||||||
|
South Central Force Main ReplacementsProject (A): Central Valley/Fairgrounds Final Design Report and related documents for Projects A & B: GeoTech Report Traffic Report Wetlands and Stream Delineation Report Project: Central Valley/Fairgrounds Force Main Work The Central Valley/Fairgrounds force main work consists of replacing
approximately 3,300 feet of 12-inch asbestos cement pipe that conveys sewage
from Lift Station 34, north along Central Valley Road NW to the intersection
of Holland Road, opposite Lift Station 5. Over the years, several leaks have
occurred, including some instances of spills to Mosher Creek, located just
south of Lift Station 34. The pipeline has been subjected to hydraulic
pressure surges that may have contributed to the leakage problems. Finally, the project will also take advantage of the replacement of the 12-inch asbestos pipe to install a tight-line through, along Fairgrounds Road, to Lift Station 6. At present, the force mains from Lift Stations 5 and 34 converge in a manhole at the intersection of Central Valley Rd. and Fairgrounds Rd. The flow continues from this point in an 8-inch line. This restriction in the system has been a point of surcharging and subsequent odor problems which are likely to worsen as flow increases from the various service areas. Schedule: Budget Project: Techite Line Replacement The techite line replacement project consists of replacing approximately 6,500 feet of 30-inch Techite pipe beginning at the intersection of NE Paulson Road and Kelly Court NE, proceeding north along Kelly Court NE, crossing Madison Road, and terminating at the Central Kitsap Treatment Plant (CKTP). This force main is a critical leg of the conveyance network: it serves the entire southerly area of the South Central service area, which is comprised of over 22 square miles, conveying this flow of between 2,000 to 4,500 gpm to the Central Kitsap Treatment Plant. The Techite line was installed in the late 1970s. Although it has not experienced problems to date, this particular type of pipe is known to be prone to failure. Techite pipe was manufactured in the 1970s using reinforced fiberglass. When compared to other flexible/plastic pressure pipe now being widely used – e.g. PVC or HDPE pipe – techite’s wall thickness is thin and this likely has contributed to the failures that have occurred throughout the United States. Because this force main is now on the order of 30 years old and situated in a major fault zone, it is of concern. The pipe is also situated near several creeks and a break could result in significant damage to local surface waters. Schedule: Budget Project: Solids Handling Upgrades at Central Kitsap Treatment Plant The 1994 Kitsap County Wastewater Division Facilities Plan recommended
upgrades to the solids handling process equipment at the Central Kitsap
Treatment Plant. The original facility was constructed in 1975 and the
existing process equipment is at capacity and at the end of its design life
of approximately 30 years. In addition, by July 1, 2012 WAC 173-308-205 will
be requiring more stringent removal of solids from the wastestream,
necessitating replacement of the existing screening equipment at the plant.
This project will bring the plant into compliance with the WAC, as well as
enhancing operations and maintenance, emergency preparedness, capacity for
existing flows, and effluent quality. Project Elements:
Schedule: Project Budget Central Kitsap Treatment Plant Headworks Replacement The 1994 Kitsap County Wastewater Division Facilities Plan recommended upgrades to the solids handling process equipment at the Central Kitsap Treatment Plant. The original facility was constructed in 1975 and the existing process equipment is at capacity and at the end of its design life of approximately 30 years. In addition, by July 1, 2012 WAC 173-308-205 will be requiring more stringent removal of solids from the wastestream, necessitating replacement of the existing screening equipment at the plant. This project will consist of the replacement of the headworks structure and the screens at the septage receiving station, bringing this function of wastewater treatment at the plant in compliance with the requirement. The headworks structure includes influent flow monitoring and measurement, grit removal, and screening. The new facility will also reduce odor at the headworks, which has been an intermittent problem to the neighborhood surrounding the treatment plant. The screens selected for installation at CKTP will be compatible with future water reclamation functions, should those be implemented. Schedule: Project Budget Staff Contact: Barbara Zaroff P.E., 360-337-5777 Kitsap County Public Works |
Updated:
October 30, 2009
|
||||||||||||||||||
| Privacy Policy | Disclaimer | Comments/email | ||||||||||||||||||